Choose the mix ratio and the volume of finished concrete. The calculator gives the bags of cement and the volumes of sand and stone chips, in cubic metres and cubic feet.

Mix ratio (cement : sand : stone)

Dry volume = 10 × 1.54 = 15.40 cum, shared over 7 parts

Cement
63.4 bags (2.20 cum)
Sand
4.40 cum (155 cft)
Stone chips
8.80 cum (311 cft)

One 50 kg bag = 0.0347 cum. Add your site wastage.

How it is worked out

  1. 1

    Dry materials contain voids, so one cubic metre of placed concrete needs 1.54 cubic metres of dry cement, sand and chips.

  2. 2

    The dry volume is shared between the materials in the mix ratio: for 1:2:4, one part in seven is cement, two are sand and four are chips.

  3. 3

    Cement is converted to bags at 0.0347 cubic metre (1.25 cubic feet) for a 50 kg bag.

A worked example

Ten cubic metres of 1:2:4 concrete

  1. 01Dry volume = 10 × 1.54 = 15.4 cum
  2. 02Cement = 15.4 × 1 ÷ 7 = 2.2 cum = 63.4 bags
  3. 03Sand = 15.4 × 2 ÷ 7 = 4.4 cum
  4. 04Stone chips = 15.4 × 4 ÷ 7 = 8.8 cum

Answer63.4 bags of cement, 4.4 cum of sand, 8.8 cum of chips

What to watch for

  • This is for nominal mixes by volume. A designed mix (25 MPa and above) is batched by weight from the mix design.
  • Deduct nothing for reinforcement in ordinary members; the difference is smaller than site wastage.
  • Sand bulks when damp. Volume measured on site is not the same as dry volume.

Questions people ask

Why 1.54?
It allows for the voids in loose dry materials and for the usual loss in mixing and placing. Some engineers use a figure between 1.50 and 1.57.
How many bags of cement in 1 cum of 1:2:4?
About 6.3 bags.
Is the factor the same for mortar?
No. Mortar has no coarse aggregate; the usual factor is 1.33.