CalculatorConstruction cost calculator for Bangladesh
Choose the kind of building, its size, the location, the finish and the ground. You get the most likely construction cost, a narrow band around it, the rate per square foot and every step of the arithmetic.
Deep foundation: piles
Most likely cost
Tk 4.70 crore
Tk 4.47 crore to Tk 4.94 crore · Tk 3,265 per sft
- Base rate, apartment building
- Tk 2,750 per sft
- × location, Dhaka city
- 1.06
- × finish, standard
- 1
- × ground, soft or filled land
- 1.12
- = Rate
- Tk 3,265 per sft
- × 2,400 sft × 6 floors
- 14,400 sft
- = Most likely cost
- Tk 4,70,00,000
- Band, 5% either side
- Tk 4.47 crore to Tk 4.94 crore
Included, as a typical share of the figure
- Foundations and structure, 48%
- Tk 2.26 crore
- Civil works and finishes, 34%
- Tk 1.60 crore
- Plumbing, electrical and services, 18%
- Tk 84.6 lakh
Not included: land, approvals, design fees, VAT and AIT. A budget figure for planning; a priced BOQ from the drawings gives the real one.
Start a BOQ for this buildingHow it is worked out
- 1
Each kind of building has a base rate per square foot. In reinforced concrete: apartment building Tk 2,750, office or shops Tk 3,300, factory Tk 2,800, hospital or school Tk 3,800. In steel, per square foot of ground floor: warehouse Tk 1,350, factory Tk 1,550, showroom or commercial Tk 1,900.
- 2
The rate is multiplied by a location factor, from 0.95 in Rangpur to 1.06 in Dhaka city, with Gazipur, Narayanganj, Savar as 1.
- 3
For a concrete building the finish (basic 0.85, standard 1, premium 1.3) and the ground (firm ground 1, medium or mixed soil 1.05, soft or filled land 1.12, not sure yet 1.06) multiply the rate again, and each floor above six adds 1%, up to 10%.
- 4
For a steel building the eave height (6 m 0.94, 8 m 1, 10 m 1.07, 12 m 1.15) and an overhead crane (5 t 1.06, 10 t 1.1, 20 t 1.15, 30 t 1.2, 50 t 1.3) multiply the rate.
- 5
The finished rate is multiplied by the total floor area (the ground-floor area for steel). The answer is the most likely cost; the band is 5% either side, or 8% when the ground is not yet known.
A worked example
A six-storey apartment building, 2,400 sft a floor, in Dhaka city, standard finish, on soft or filled land
- 01Base rate, apartment building: Tk 2,750 per sft
- 02× location, Dhaka city: 1.06
- 03× finish, standard: 1
- 04× ground, soft or filled land: 1.12
- 05Rate: Tk 3,265 per sft
- 06× 2,400 sft × 6 floors: 14,400 sft
- 07Most likely cost: Tk 4,70,00,000
- 08Band, 5% either side: Tk 4.47 crore to Tk 4.94 crore
AnswerTk 4.70 crore, between Tk 4.47 crore and Tk 4.94 crore
What to watch for
- Land, approvals, design fees, VAT and AIT are outside the figure. Add them to reach the money you need in hand.
- The ground moves the cost of the whole building. Until a soil test is done, choose "Not sure yet": the rate sits between raft and piles and the band widens.
- The steel rate prices the whole building, with its foundations and floor slab, but not the crane machinery, and not a mezzanine or upper steel floors: the quick budget on the home page adds those.
- A rate per square foot cannot see your drawings. Basements, long spans, unusual shapes and special services change the cost, and only a priced BOQ shows by how much.
When to use it
Use it at the very start, before there are drawings: to see whether a plot and a budget fit each other, to compare a concrete factory with a steel one, or to check a figure someone has quoted you per square foot.
Enter the area of one floor and the number of floors. For a steel building enter the ground-floor area, because the steel rate already prices the whole shed.
Where the rates come from, and their limits
The rates were set in November 2026 from published Bangladesh cost ranges and 2026 prices of rod and cement, raised to include basic plumbing, electrical work and site works. They are the same rates as the quick budget on the home page.
Concrete buildings are priced up to 20 floors (apartment building), 20 floors (office or shops), 12 floors (factory), 15 floors (hospital or school). Taller buildings need their own study.
Prices move. Treat the result as today's planning figure and price the real quantities before you commit money: start a BOQ, measure the work and rate it on the PWD Schedule of Rates or your own analysed rates.
Questions people ask
- What is the construction cost per square foot in Bangladesh?
- It depends on the building, the place, the finish and the ground. For an apartment building of standard finish on firm ground this calculator uses Tk 2,750 per sft in Gazipur, Narayanganj, Savar; the same building on piles in Dhaka city comes to Tk 3,265 per sft.
- Is the price of land included?
- No. The figure is the cost of building: structure, civil works and finishes, and plumbing, electrical and services. Land, approvals, design fees, VAT and AIT are not in it.
- How accurate is the result?
- It is a budget figure for planning, given as one most likely cost with a band of 5% either side. It is not a quotation. A BOQ measured from the drawings and priced item by item replaces it once the design exists.
- Why does a steel building use only the ground-floor area?
- The steel rate is for the whole building, frame, cladding, foundations and floor slab, per square foot of ground floor. A 30,000 sft warehouse in Gazipur, Narayanganj, Savar at 8 m eave height comes to about Tk 4.05 crore.
- How is this different from the quick budget on the home page?
- Both use the same rates, so they give the same answer for the same building. The quick budget also covers structural assessment, retrofitting, mezzanines and a second crane; this page shows the arithmetic line by line.