Engineering articlesPEB or RCC for a factory building in Bangladesh: cost, time and foundations

When a pre-engineered steel building is the better choice for a shed, a warehouse or a production hall, when reinforced concrete still wins, and what each costs per square foot in 2026.

By , Founder & CEOPublished 18 October 2026Updated 24 November 20266 min read

PEB or RCC for a factory building in Bangladesh: cost, time and foundations
Picture: generated with AI and edited by Estimatrix.

Every new factory in Gazipur, Savar, Narayanganj or Chattogram meets the same early question: build the production hall in reinforced concrete, or as a pre-engineered steel building (PEB)? For a single-storey hall the steel building is usually cheaper and faster. For several heavily loaded floors, concrete still wins.

What a PEB is

A steel building whose frames are built up from plate and tapered to the load, with cold-formed purlins and girts and colour-coated sheeting, made in a factory and bolted together on site. Prime Base Engineering explains each part, from the primary frames to the anchor bolts, in pre-engineered building components explained. This page does the arithmetic of the choice.

A single-storey factory, both ways

RCC factory

Tk 5.60 crore

Tk 2,800 per sft of floor area.

Cost in 2026

These are the rates behind the Estimatrix budget calculator, for a complete factory building with a standard specification in the Gazipur, Narayanganj and Savar belt.

RCC factory PEB factory
Most likely cost Tk 2,800 per sft of floor area Tk 1,550 per sft of ground-floor area
Basis Whole building, standard finish, firm ground Whole building with foundations and floor slab, eave height 8 m

A warehouse in steel is about Tk 1,350 per sft. A taller shed costs more, about 15% more at 12 m than at 8 m, and overhead cranes add a further premium for heavier columns and crane beams. All figures exclude land, approvals, design fees, VAT and AIT.

The comparison is fair only for one storey. An RCC building's rate is per square foot of every floor, so a four-storey concrete factory gives four floors on one piece of land; a steel shed gives one, plus any mezzanine at about Tk 1,200 per sft.

When concrete still wins

For several floors with heavy loads, such as garment floors, a concrete frame usually comes out ahead, and very small sheds rarely carry the fixed costs of steel fabrication. Many factories end up hybrid: concrete for the multi-storey office and utility block, steel for the production hall and the warehouse.

How the two systems are built, and how they behave in earthquakes, wind, fire and Bangladesh's damp climate, is compared in Prime Base Engineering's PEB vs RCC factory comparison, with a decision guide.

Mistakes we see often

  • Comparing a steel price without foundations and floor against a complete concrete building.
  • Forgetting the crane when the frame is priced, then adding it later at a much higher cost.
  • Choosing the eave height before the machinery layout is known.
  • Leaving out sheeting, gutters, doors and ventilators from the steel quotation.

Estimating a PEB in Estimatrix

Structural steel items use a steel take-off: sections chosen from a table (I and channel sections, angles, purlins, hollow sections) or plates by length × width × thickness at 7,850 kg per cubic metre, giving kilograms or tonnes directly. Add the anchor bolts, base plates, primer, sheeting, and the concrete pedestals and floor. To compare the two options for your own area and height, use the budget calculator.

A worked comparison for a 20,000 sft hall

A single-storey production hall of 20,000 sft in the Gazipur belt, standard specification, firm ground.

Option Rate Budget
RCC factory Tk 2,800 per sft 20,000 × 2,800 = Tk 5.6 crore
PEB factory, 8 m eave Tk 1,550 per sft 20,000 × 1,550 = Tk 3.1 crore
PEB warehouse, 8 m eave Tk 1,350 per sft 20,000 × 1,350 = Tk 2.7 crore

A mezzanine over a quarter of the steel factory adds 5,000 × 1,200 = Tk 60 lakh, which brings it to Tk 3.7 crore for 25,000 sft of usable floor.

These are most likely figures with about 5% either side, and they exclude land, approvals, design fees, VAT and AIT.

How height and cranes change the steel price

The steel rate above is for an 8 m eave and no crane. The eave height is the clear height the process needs, plus the depth of the frame and any crane.

Eave height Change PEB factory rate
6 m (20 ft) about 6% less Tk 1,457 per sft
8 m (26 ft) the base rate Tk 1,550 per sft
10 m (33 ft) about 7% more Tk 1,659 per sft
12 m (40 ft) about 15% more Tk 1,783 per sft

An overhead crane needs heavier columns, runway beams and deeper foundations. As a guide the premium on the shed rate is about 6% for a 5 tonne crane, 10% for 10 tonnes, 15% for 20 tonnes and 20% for 30 tonnes. A second crane in the same bay adds about half its own premium, because the runway and the columns are shared. The crane machine is priced separately.

So a 20,000 sft factory with a 10 tonne crane at an 8 m eave is about 1,550 × 1.10 = Tk 1,705 per sft, or Tk 3.4 crore.

What to give a PEB supplier before asking for a price

A steel quotation is only as good as the brief behind it. Send the same sheet to every supplier.

  1. Clear width and length, and whether internal columns are acceptable.
  2. Clear height under the frame or under the crane hook.
  3. Crane: capacity, span, and how many.
  4. Mezzanine: area, and the load it must carry.
  5. Roof and wall sheeting: type, thickness, insulation, skylights.
  6. Openings: doors, shutters, ventilators, louvres.
  7. Location, so the wind load for the site is used.
  8. What is in the price: foundations, floor slab, anchor bolts, erection, transport, painting.

Questions people ask

Can a steel building have more than one floor? Yes. A mezzanine or a full upper floor on a steel deck is common, at about Tk 1,200 and Tk 1,500 per sft of its own area. For several floors with heavy loads, compare a concrete frame before deciding.

Can the building be extended later? Yes, if it is planned. Ask for the end frame to be designed as an ordinary frame, so bays can be added without rebuilding it.

Is a supplier's price per sft the same as these rates? Often not. A steel quotation may cover the frame and the sheeting only, while the rates here are for the whole building with its foundations and floor slab. Add what is missing before you compare.

How do I compare a PEB rate with an RCC rate fairly? Per square foot of usable floor. The RCC rate counts every floor, the PEB rate only the ground floor, so add a mezzanine or an upper floor at its own rate before comparing the totals.

Getting a design

Prime Base Engineering designs, supplies and erects PEB buildings. For a design and a firm price for your site, use the contact page.

Try itMaterials for nominal-mix concrete
Mix ratio (cement : sand : stone)

Dry volume = 10 × 1.54 = 15.40 cum, shared over 7 parts

Cement
63.4 bags (2.20 cum)
Sand
4.40 cum (155 cft)
Stone chips
8.80 cum (311 cft)

One 50 kg bag = 0.0347 cum. Add your site wastage.

#peb#steel#factory#value engineering