Engineering articlesConstruction cost per square foot in Bangladesh (2026): rates, adjustments and checks

What a building costs per square foot in Bangladesh in 2026 for apartments, offices, factories, hospitals and steel sheds, what moves the figure, and how to use it to check a BOQ.

By , Founder & CEOPublished 28 October 2026Updated 24 November 20266 min read

Construction cost per square foot in Bangladesh (2026): rates, adjustments and checks
Photo: Design Hills / Unsplash

A cost per square foot is the first number an owner asks for and the last check an engineer makes on a finished BOQ. It is useful for both, as long as everyone knows what is inside the figure and what is not.

To get the figure for your own building straight away, use the construction cost calculator: choose the kind of building, its size, location, finish and ground, and it applies the rates below and shows every step of the arithmetic.

Rates for a new RCC building

These are the rates behind the Estimatrix budget calculator, the same ones Prime Base Engineering uses for a first budget. They are for a complete building with a standard finish, on firm ground, in the Gazipur, Narayanganj and Savar belt, per square foot of total floor area.

Building Most likely cost, Tk per sft
Apartment building 2,750
Factory 2,800
Office or shops 3,300
Hospital or school 3,800

They include the structure, the civil works and finishes, and basic plumbing, electrical and site works. They exclude land, approvals, design fees, VAT and AIT, and special equipment such as lifts and generators.

Tk per sft, and what moves it

Basic finish

Tk 2,338

About 15% less.

Rates for a steel building

A pre-engineered steel building (PEB) is priced per square foot of ground-floor area, for the whole building with its foundations and floor slab, at an eave height of 8 m.

Building Most likely cost, Tk per sft
Warehouse 1,350
Factory 1,550
Showroom or commercial 1,900

A mezzanine adds about Tk 1,200 per sft of its own area, and a full upper steel floor about Tk 1,500.

What moves the figure

Change Effect on the rate
Basic finish instead of standard about 15% less
Premium finish about 30% more
Dhaka city about 6% more
Chattogram about 5% more
Rajshahi, Rangpur about 4 to 5% less
Raft or combined footings about 5% more
Piles on soft or filled land about 12% more
Each floor above six about 1% more, up to 10%
Steel shed 12 m high instead of 8 m about 15% more

A worked example

A six-storey apartment building of 2,400 sft per floor in Dhaka city, standard finish, on piles.

  • Floor area = 2,400 × 6 = 14,400 sft
  • Rate = 2,750 × 1.06 × 1.12 = Tk 3,265 per sft
  • Budget = 14,400 × 3,265 = about Tk 4.7 crore

Treat it as a most likely figure with a few percent either side, not as a price.

Material thumb rules for RCC buildings

Indicator Typical range
Reinforcement 3.5 to 5.5 kg per sft, more in tall or seismically detailed frames
Cement 0.40 to 0.55 bag per sft
Bricks 8 to 12 per sft

Using the figures to check a BOQ

A number far outside the range is not always wrong, but it deserves a second look.

  • Steel per sft much too high: a length in feet multiplied by a weight per metre, or a slab measured twice.
  • Cement per sft too low: plaster or flooring items are missing.
  • Cost per sft too low: a whole trade is missing, such as sanitary, electrical or site development.

Once you enter the built-up area, Estimatrix works out the cost, the steel and the cement per sft of your project and marks any that fall outside the usual range.

Where the rates come from

They are built from published 2025 and 2026 cost ranges for Bangladesh, raised to include basic services and site works, and from 2026 material prices: 60-grade rod at about Tk 85,000 to 1,00,000 a tonne and cement at about Tk 475 to 580 a bag. Prices move, so check today's market prices before relying on an old budget.

Three more worked budgets

The method is always the same: floor area × rate × the adjustments that apply. Every rate and factor below is one of those in the tables above.

A five-storey apartment building in Rajshahi, basic finish, firm ground. 1,800 sft per floor.

  • Floor area = 1,800 × 5 = 9,000 sft
  • Rate = 2,750 × 0.85 × 0.96 = Tk 2,244 per sft
  • Budget = 9,000 × 2,244 = about Tk 2.0 crore

A ten-storey office in Dhaka city, premium finish, firm ground. 2,500 sft per floor. Four floors are above six, so the height adds 4%.

  • Floor area = 2,500 × 10 = 25,000 sft
  • Rate = 3,300 × 1.30 × 1.06 × 1.04 = Tk 4,729 per sft
  • Budget = 25,000 × 4,729 = about Tk 11.8 crore

A four-storey school in Chattogram, standard finish, on a raft. 3,000 sft per floor.

  • Floor area = 3,000 × 4 = 12,000 sft
  • Rate = 3,800 × 1.05 × 1.05 = Tk 4,190 per sft
  • Budget = 12,000 × 4,190 = about Tk 5.0 crore

The adjustments multiply. Two of 5% each make 10.25%, not 10%.

A worked budget for a steel building

A warehouse of 20,000 sft with a 10 m eave, in the Gazipur belt, with a mezzanine over a quarter of the floor.

  • Shed rate = 1,350 × 1.07 = Tk 1,445 per sft (a 10 m eave costs about 7% more than 8 m)
  • Shed = 20,000 × 1,445 = Tk 2.89 crore
  • Mezzanine = 5,000 × 1,200 = Tk 60 lakh
  • Budget = about Tk 3.5 crore

A 6 m eave costs about 6% less than 8 m. An overhead crane adds a premium to the shed rate for heavier columns, runway beams and foundations: about 6% for a 5 tonne crane, 10% for 10 tonnes and 15% for 20 tonnes. The crane machine itself is not in the figure.

How to work out the floor area

The rate is only as good as the area it is multiplied by. Use the same definition the rates use.

  1. Take the outside dimensions of each floor, walls included.
  2. Count every floor that is built: ground floor, upper floors and any roof-top rooms.
  3. Include stairs, lift lobbies, verandas and covered corridors. They are built and finished like the rest.
  4. Leave out open terraces, the open roof and uncovered parking.
  5. For a steel building, use the ground-floor area of the shed, and add a mezzanine by its own area.

Questions people ask

How sure is the figure? Treat it as the most likely cost with about 5% either side for a known foundation. For the six-storey example above, Tk 4.7 crore means about Tk 4.5 to 4.9 crore. Where the soil has not been tested, the foundation alone can move it more.

Why does a hospital or a school cost more per sft than an apartment? Larger spans, heavier floor loads, wider corridors and stairs, and more services in every room.

Does a taller building cost more per sft? Yes, a little. Each floor above six adds about 1%, up to 10%, because the columns and foundations carry more.

Can I use the figure for a tender? No. It tells you whether a project is affordable. A tender needs a measured BOQ.

From a rate to a real estimate

A cost per square foot is for deciding whether a project is feasible. A tender needs a measured BOQ. Try your own building in the construction cost calculator, then create a BOQ when the drawings are ready.

For a factory, the costs that sit outside the building rate (the brief, the site investigation, price protection, contingency and cash flow) are set out step by step in Prime Base Engineering's guide to planning an industrial construction budget.

#cost#budget#thumb rules

Related articles