Engineering articlesWhat is a bill of quantities (BOQ)? A practical guide for Bangladesh

What a BOQ is, what each column means, how it is measured and priced, and the mistakes that cost money, explained with a small worked example.

By , Founder & CEOPublished 30 October 2026Updated 24 November 20267 min read

What is a bill of quantities (BOQ)? A practical guide for Bangladesh
Picture: generated with AI and edited by Estimatrix.

A bill of quantities (BOQ) is a list of every item of work in a project, each with a unit and a measured quantity, so that the work can be priced line by line. With a rate beside each line it becomes the estimate, then the tender, and later the basis of every bill the contractor submits.

What each line of a BOQ contains

A BOQ line has six parts, and each one answers a question.

Column Question it answers Example
Item number Which standard item is this? 07.1.1
Description What exactly is to be done, to what specification? RCC in footings, 1:2:4, stone chips
Unit How is it measured? cum
Quantity How much of it is there? 42.50
Rate What does one unit cost? Tk per cum
Amount Quantity × rate Tk

On public work the item number is the number in the PWD Schedule of Rates, which fixes the description, the unit and the rate together. On private work the numbering is your own, but the discipline is the same: one line, one clearly described piece of work.

One list, used five times

Drawings

The work is read from the drawings.

How the lines are grouped

Lines are grouped under headings that follow the order of construction: earthwork, foundation, reinforced concrete, brickwork, plaster, flooring, doors and windows, painting, sanitary and plumbing, electrical, external works. Each group has a sub-total, and the sub-totals form the abstract of cost, the one page an owner actually reads. The full sequence is in the order of items in a building BOQ.

Where the quantities come from

Every quantity is the result of a measurement, and the working is kept on a measurement sheet: number × length × breadth × height, line by line, with deductions for openings.

A small example. Six column footings, each 5 ft × 5 ft × 1.5 ft:

  • 6 × 5 × 5 × 1.5 = 225 cft of concrete in footings

That one line of working is what lets a checker, an auditor or you in six months confirm where 225 came from. A BOQ without its measurement sheet is a list of numbers nobody can defend.

Where the rates come from

A rate is either taken from a schedule or built by a rate analysis: the materials, labour and equipment for one unit of the item, plus overhead and profit. Public estimates use the Schedule of Rates in force for the project's zone. Contractors and private owners build rates from market prices. The difference between the two is explained in PWD rate or market rate.

Who prepares it, and who uses it

The client's engineer or consultant prepares the BOQ and the official estimate. Contractors price the same quantities to tender, so their offers can be compared. The site engineer measures completed work against it for every running bill, and the final bill is the BOQ measured again as built.

This page is about preparing a BOQ. If you have received one and need to check it, Prime Base Engineering's guide on how to read a BOQ lists what to check and the red flags.

BOQ, estimate, quotation, abstract

These four are often used loosely. The BOQ is the measured list. The estimate is the BOQ priced by the person paying. The quotation is the BOQ priced by the person offering to build. The abstract is the summary by section. This article sets them side by side.

Mistakes that cost money

  • Items missing between trades. Damp-proof course, curing, scaffolding, soil disposal and testing belong to nobody unless the BOQ names them.
  • Double counting. The concrete of a beam measured through the column, and the column measured through the beam.
  • Wrong zone or old edition. The item is right and the rate is not.
  • Reinforcement without laps and chairs. The steel quantity is then several percent short.
  • Openings not deducted from brickwork, or deducted from plaster on one face only.
  • Units mixed. Feet on the drawing, metres in the rate.

A small bill, priced from end to end

Take the six footings of 5 ft × 5 ft × 1.5 ft from the example above and add the work under them: a pit 6.5 ft square and 5 ft deep for each, 3 inches of sand, brick flat soling and 3 inches of lean concrete. The rates are examples, there to show the arithmetic.

Item Measurement Quantity Example rate (Tk) Amount (Tk)
Earthwork in excavation 6 × 6.5 × 6.5 × 5 1,267.5 cft 12 15,210
Sand filling 6 × 6.5 × 6.5 × 0.25 63.38 cft 45 2,852
Brick flat soling 6 × 6.5 × 6.5 253.5 sft 60 15,210
Lean concrete 1:3:6 6 × 6.5 × 6.5 × 0.25 63.38 cft 250 15,845
RCC in footings 6 × 5 × 5 × 1.5 225 cft 320 72,000
Sub-total, foundation 1,21,117

Five lines, each with its working, and one sub-total. The abstract of cost for this job would show a single line: Foundation, Tk 1,21,117. Reinforcement and formwork would be the next two items. They are left out here to keep the table short, and in a real bill leaving them out is exactly the mistake described above.

The units a BOQ uses

The unit is part of the item. Change the unit and you have changed what is being bought.

Work Usual unit
Earthwork, sand filling, concrete cum or cft
Reinforcement kg or metric ton
250 mm (10 inch) brickwork cum or cft
125 mm (5 inch) brickwork sqm or sft
Plaster, painting, tiles, soling, formwork sqm or sft
Skirting, pipes, railings, drains m or rft
Doors, fittings, fixtures number
Site facilities, mobilisation lump sum

Thin work is measured by area and thick work by volume. That is why a 5 inch wall and a 10 inch wall are different items with different units, and why their rates cannot be compared directly.

How the bill is used after the contract is signed

The BOQ does not retire once the price is agreed. It becomes the ruler for every payment.

Suppose the contract holds the 225 cft of footing concrete at the example rate of Tk 320.

  • First running bill. Four of the six footings are cast: 4 × 5 × 5 × 1.5 = 150 cft. The bill claims 150 × 320 = Tk 48,000.
  • Second running bill. All six are cast. The bill states 225 cft to date, less the 150 cft paid before, and claims the remaining 75 × 320 = Tk 24,000.
  • A change. The engineer deepens two footings by 6 inches: 2 × 5 × 5 × 0.5 = 25 cft more. Because the item and its rate already exist, the extra is paid at the same Tk 320, as 25 × 320 = Tk 8,000, and nobody has to negotiate.

This is the practical value of a good BOQ. When the work changes, there is already an agreed price for it.

Questions people ask

Who pays if the real quantity is more than the BOQ says? On an item-rate contract the work is measured as built and paid at the BOQ rate, so the client pays for the extra. On a lump-sum contract the contractor carries that risk, unless the drawings changed.

Does a small house need a BOQ? Yes, if you want to compare contractors. Two quotations can only be compared when both price the same list of work.

Is a BOQ the same as an estimate? No. The BOQ is the measured list. It becomes an estimate when rates are written beside it. See BOQ, estimate and quotation.

Doing it in Estimatrix

In Estimatrix the measurement sheet, the BOQ, the rate analysis, the material requisition and the budget are one linked project. Enter the footings above once and the quantity, the amount, the cement to buy and the foundation budget are all filled in, and they change together when the drawing changes. Create a BOQ online; it is free to start.