Engineering articlesBar bending schedule: cutting length, laps, hooks, bend deductions and 12 m bars

How to prepare a bar bending schedule: the cutting length formula, hooks, lap lengths, bend deductions, a worked stirrup, and fitting the cut pieces into 12 m bars.

By , Founder & CEOPublished 12 October 2026Updated 23 November 20268 min read

Bar bending schedule: cutting length, laps, hooks, bend deductions and 12 m bars
Picture: generated with AI and edited by Estimatrix.

A bar bending schedule (BBS) is a table of every bar in a member: its mark, shape, diameter, number and cutting length. The site cuts and bends from it, and it gives the most accurate steel quantity an estimate can have.

What a line of the schedule holds

Column What it tells the site
Bar mark Which bar on the drawing this is
Diameter 10, 12, 16 mm and so on
Shape Straight, L, U, stirrup, crank
Members × bars per member How many pieces to make
Cutting length How long to cut each piece before bending
Weight Pieces × cutting length × unit weight

Cutting length of one stirrup

Perimeter

1,280 mm

2 × (220 + 420) inside the cover.

The cutting length

Cutting length = straight lengths + hooks + laps − bend deductions

Each of the three corrections has its own rule.

Hooks

  • 90 degree hook: commonly 9d is added for each hook, where d is the bar diameter.
  • 135 degree hook on stirrups and ties, the hook used in seismic detailing: the code asks for an extension of at least 6d and not less than 75 mm, and many engineers allow 10d. Estimatrix uses the larger of 10d and 75 mm unless you change it in the bar bending rules.

Laps

A lap is the overlap where one bar ends and the next begins. Its length comes from the structural design: it depends on whether the bar is in tension or compression, on the concrete grade and on the position of the bar. Working values of 40d for small bars and 50d to 60d for larger ones are common, but the drawing decides. Follow the drawing.

Bend deductions

A bar stretches a little when it is bent, so the length measured along the outside of the shape is more than the piece that has to be cut.

Bend Deduct
45 degrees 1d
90 degrees 2d
135 degrees 3d

A worked example: one stirrup

A beam 300 × 500 mm with 40 mm cover, stirrups of 10 mm bar with two 135 degree hooks.

  • Inside the cover the stirrup measures 300 − 80 = 220 mm by 500 − 80 = 420 mm
  • Perimeter = 2 × (220 + 420) = 1,280 mm
  • Two hooks at 10d = 2 × 100 = 200 mm
  • Bends: three of 90 degrees and two of 135 degrees = 3 × 2d + 2 × 3d = 12d = 120 mm
  • Cutting length = 1,280 + 200 − 120 = 1,360 mm
  • Weight of one stirrup = 1.36 m × 0.617 kg/m = 0.84 kg

A 6 m beam with stirrups at 150 mm has 41 of them, about 34 kg of steel that a rough estimate often leaves out.

Weight

Weight = members × bars per member × cutting length × unit weight, with the unit weight from D² ÷ 162 kg per metre. See rebar weight calculation.

Stock length and off-cuts

Bars are sold 12 m (39.37 ft) long. A good cutting list fits short pieces into what is left of long ones. A bar that has to be longer than 12 m is made of two with a lap. The difference between the weight in the schedule and the weight you have to buy is the off-cut percentage; try to keep it below about 5 to 8%.

Chair bars

The top layer of steel in a slab or a raft stands on chairs, often 12 mm bars at about one per square metre. They are easy to forget and quick to add.

Mistakes we see often

  • Laps left out of long bars in beams and columns.
  • Hooks counted on one end only.
  • The clear cover deducted once instead of on both sides.
  • The same bar entered under two bar marks.

A worked example: a beam bar with two hooks

A bottom bar of 16 mm in a beam 6.0 m long, with 40 mm cover at each end and a 90 degree hook at each end.

  • Straight length inside the cover = 6,000 − 2 × 40 = 5,920 mm
  • Two hooks at 9d = 2 × 9 × 16 = 288 mm
  • Two bends of 90 degrees at 2d = 2 × 2 × 16 = 64 mm
  • Cutting length = 5,920 + 288 − 64 = 6,144 mm
  • Weight = 6.144 m × 1.578 kg/m = 9.70 kg

A worked example: a cranked bar in a slab

A bent-up bar gains length where it climbs from the bottom of the slab to the top. For a 45 degree crank the extra length is 0.42 × D, where D is the vertical height of the crank, measured between the centres of the bar at the bottom and at the top.

A slab 125 mm thick with 20 mm cover top and bottom and a 10 mm bar:

  • D = 125 − 2 × 20 − 10 = 75 mm
  • Extra length for one crank = 0.42 × 75 = 31.5 mm

For a bar with a straight length of 4,000 mm and a crank near each end:

  • Two cranks = 2 × 31.5 = 63 mm
  • Four bends of 45 degrees at 1d = 4 × 10 = 40 mm
  • Cutting length = 4,000 + 63 − 40 = 4,023 mm
  • Weight = 4.023 × 0.617 = 2.48 kg

A worked example: a bar longer than 12 m

A column bar of 20 mm has to run 15 m through several floors. Stock bars are 12 m, so it is made of two pieces with a lap. Take a lap of 50d for the arithmetic; the drawing gives the real value.

  • Lap = 50 × 20 = 1,000 mm
  • Total length to cut = 15.0 + 1.0 = 16.0 m, for example one piece of 12 m and one of 4 m
  • Weight = 16.0 × 2.466 = 39.5 kg

Laps in neighbouring bars are staggered, so they do not all fall at one level. Follow the positions the drawing shows, and never place a lap where the drawing forbids one.

A filled-in schedule

The beam from the examples above: four of the bottom bars, and the 41 stirrups worked out earlier.

Mark Dia Shape Nos Cutting length Total length Weight
B1 16 mm straight, two 90° hooks 4 6,144 mm 24.58 m 38.8 kg
S1 10 mm stirrup, two 135° hooks 41 1,360 mm 55.76 m 34.4 kg
Total 73.2 kg

Total the schedule by diameter as well as by member. Steel is ordered by diameter.

Cutting stirrups from 12 m bars

  • One 12 m bar gives 12,000 ÷ 1,360 = 8 stirrups, with 12,000 − 8 × 1,360 = 1,120 mm left
  • 41 stirrups need 41 ÷ 8 = 5.1, so 6 bars
  • The off-cut of each full bar is 1,120 ÷ 12,000 = 9.3%

An off-cut of 1,120 mm is not waste if a shorter piece can be cut from it: a chair, a short tie or a link for a smaller member. This is why a cutting list is made for the whole floor at once, not member by member.

Checks before the bars are cut

  1. Check the bar mark, the diameter and the number against the drawing, not against memory.
  2. Check the cover used in the schedule against the cover in the drawing notes. Footings, columns and slabs have different covers.
  3. Add up the cutting length of one bar by hand and compare it with the schedule.
  4. Bend one bar of each shape first and try it in the formwork before the rest are bent.
  5. Tag each bundle with its bar mark.

Questions people ask

Why is the bend deduction made? A bar is measured along its outside faces on the drawing, but it bends around a curve and stretches slightly. The deduction corrects the sum of the outside lengths to the length that must be cut.

Are the hook and bend rules the same everywhere? No. The values here are common working values. The code and the drawing notes of your project govern, and offices keep their own tables. Use one set of rules through the whole schedule.

Is a lap added to every bar? Only to bars that are longer than the stock length or that are stopped and continued by the design. A short bar that fits in one piece has no lap.

Is the weight in the schedule the weight to buy? No. Add the off-cuts that cannot be reused. The schedule gives the weight fixed in the member; the cutting list gives the weight to buy.

In Estimatrix

The BBS sheet sets the lap when you choose a diameter, has columns for 135 degree hooks, works out the cutting length and the weight of each row, and totals the steel by diameter. It also fits the cut lengths into 12 m bars and gives the quantity to buy. Tie the bars to their BOQ item, or let the reinforcement quantity of the BOQ come from the schedule.

Try itRebar weight by D² ÷ 162
Bar diameter

16² ÷ 162 = 1.580 kg per metre

× 12 m × 10 bars

189.6 kg (0.190 tonne)

Add laps, hooks and chairs as your drawing requires.

#bbs#rebar#detailing

Related articles