Engineering articlesEstimating the substructure: earthwork, sand filling, soling and lean concrete

How to measure everything under a footing, in the order it is built: excavation with working space, sand filling, brick flat soling, lean concrete and back-filling, with a worked example.

By , Founder & CEOPublished 14 October 2026Updated 24 November 20266 min read

Estimating the substructure: earthwork, sand filling, soling and lean concrete
Photo: Scott Blake / Unsplash

The work under a footing is small in cost and first in the BOQ, and it is where a careless estimate starts to drift. Measure it in the order it is built: dig, fill with sand, lay the soling, cast the lean concrete, and only then the footing itself.

1. Earthwork in excavation

Measure the pit or trench with its working space, not the footing alone. People need room to fix formwork, commonly 150 to 300 mm beyond the footing on each side, and more in a deep pit. The depth is taken from the existing ground level.

Volume = length × breadth × depth, in cum or cft.

Say in the description what the soil is and how deep the excavation goes. Deep or wet excavation and dewatering are separate items with their own rates.

Under one 5 ft × 5 ft footing

Excavation

211 cft

Pit 6.5 × 6.5 ft with working space, 5 ft deep.

2. Sand filling

Sand is spread in layers and compacted under the footings and in the plinth. Measure the compacted volume, because that is what the drawing shows. Sand is bought loose, and loose sand is roughly 1.2 to 1.25 times its compacted volume, so allow for that when you order.

3. Brick flat soling

One layer of bricks laid flat on the compacted sand, with the joints filled with sand. It is measured by area, in sqm or sft, under the footings and the floors.

4. Lean concrete (CC 1:3:6)

A thin bed of concrete, usually 75 mm (3 inches), over the soling. It gives a clean, level surface on which the footing steel can be fixed. It is measured by volume, and its cement, sand and chips follow the dry-volume method.

5. Polythene sheet

Where the specification asks for a polythene sheet between the soling and the concrete, measure it by area.

A worked example: one footing

A footing 5 ft × 5 ft in a pit 5 ft deep, with 9 inches of working space on each side, 3 inches of sand, flat soling and 3 inches of lean concrete.

  • Pit = 6.5 × 6.5 = 42.25 sft; excavation = 42.25 × 5 = 211 cft
  • Sand filling = 42.25 × 0.25 = 10.6 cft compacted, about 13 cft loose
  • Brick flat soling = 42.25 sft
  • Lean concrete = 42.25 × 0.25 = 10.6 cft

Measured on the footing size alone, the excavation would be 125 cft: four tenths of the digging would be missing from the bill.

6. Then the footing

Reinforcement, formwork and concrete of the footing follow, then the short columns and grade beams, the damp-proof course and the plinth filling.

Back-filling

The earth put back around the foundation is a separate item, earth filling around foundations or in the plinth. What is left over has to be carried away, and that is an item too if the site cannot keep it.

Mistakes we see often

  • Excavation measured on the footing size, without working space.
  • Sand ordered at its compacted volume.
  • Soling measured by volume instead of area.
  • Back-filling and disposal of surplus earth forgotten.

Materials for the footing in the example

The quantities above become an order once the materials are worked out.

Lean concrete, 10.6 cft of 1:3:6.

  • Dry volume = 10.6 × 1.54 = 16.3 cft; parts = 10
  • Cement = 1.63 cft = 1.3 bags
  • Sand = 4.9 cft
  • Chips = 9.8 cft

Brick flat soling, 42.25 sft. A brick laid flat covers its nominal face of 10 × 5 inches, which is 50 square inches, so there are 144 ÷ 50 = about 2.9 bricks in a square foot.

  • Bricks = 42.25 × 2.9 = about 122, before breakage

Sand filling, 10.6 cft compacted: order about 13 cft loose, as above. The joints of the soling are filled with sand too, so keep a little more on site.

A worked example: back-filling the same pit

Back-filling is the excavation less everything that now occupies the pit below ground level. Take a footing 15 inches thick and a short column of 12 × 12 inches. The sizes are examples.

  • Excavation = 6.5 × 6.5 × 5 = 211.3 cft
  • Sand filling, soling and lean concrete, 3 inches each = 3 × 42.25 × 0.25 = 31.7 cft
  • Footing = 5 × 5 × 1.25 = 31.3 cft
  • Short column, 3.0 ft high below ground = 1 × 1 × 3.0 = 3.0 cft
  • Back-filling = 211.3 − 31.7 − 31.3 − 3.0 = 145.3 cft

The earth that does not go back, 211.3 − 145.3 = 66 cft, is used in the plinth or carried away. Loose earth takes up more room than it did in the ground, so the volume to carry is larger than 66 cft.

A worked example: a trench for a wall footing

A trench 60 ft long, 3 ft wide and 3.5 ft deep, with 3 inches of sand, flat soling and 3 inches of lean concrete along its whole length.

  • Excavation = 60 × 3 × 3.5 = 630 cft
  • Sand filling = 60 × 3 × 0.25 = 45 cft
  • Brick flat soling = 60 × 3 = 180 sft
  • Lean concrete = 60 × 3 × 0.25 = 45 cft

Measure trenches along the centre line of the walls. Where two trenches meet, do not count the corner twice.

A worked example: sand filling in the plinth

A room 12 ft × 14 ft inside the grade beams, to be filled 2 ft deep.

  • Compacted volume = 12 × 14 × 2 = 336 cft
  • Sand to order, loose = 336 × 1.2 to 1.25 = about 400 to 420 cft

Fill in layers and compact each one before the next is placed. The thickness of a layer and the compaction required are given in the specification; follow it, because a floor laid on loose fill settles and cracks.

Checks on site

  • Check the depth at several points, not only at the corner where the level was set.
  • Look at the bottom of the pit before anything is placed. Soft or wet ground at founding level is a question for the engineer, not something to cover with sand.
  • Keep water out. Pump before concreting, and do not cast lean concrete into standing water.
  • Protect the sides of a deep pit. Slope them or support them as the engineer directs, and keep excavated earth and materials back from the edge.
  • Record the levels of the ground, the bottom of the pit and the top of the lean concrete. Those three numbers settle most arguments about quantities later.

Questions people ask

Is working space always paid for? It depends on the method of measurement in the contract. Some contracts pay for the footing size only and expect the rate to cover the extra digging. Read the rule before you price.

Is soling measured by number of bricks? No. It is measured by area. The brick count is for ordering.

Why is lean concrete needed under a footing? It gives a clean, level, firm surface, keeps the footing steel off the soil and stops the wet concrete losing water into the ground.

Does the lean concrete project beyond the footing? Usually it is a little wider than the footing on each side, as the drawing shows. Measure it to its own size, not to the footing size.

How is rock or hard soil priced? As a separate item with its own rate, measured separately from ordinary soil.

In Estimatrix

Add earthwork in excavation and Estimatrix suggests the items that follow it: sand filling, brick flat soling, CC 1:3:6, footing reinforcement and RCC in footing, each from the PWD Schedule of Rates for your zone. For the usual order of a whole bill, see the order of items in a building BOQ.

#earthwork#foundation#substructure