Estimatrix guidesRate analysis on the PWD Schedule of Rates: how Estimatrix builds it
Every SoR item arrives with a rate analysis: material quantities from the specification, PWD basic rates for your zone, market prices alongside and a balancing line that keeps the published rate.
By Muhammad Sarowar Hossain, Founder & CEOPublished 26 October 2026Updated 24 November 20266 min read

A rate analysis explains what one unit of work costs: the materials, labour and equipment it needs, multiplied by their rates, plus overhead, profit and VAT. A rate without one cannot be defended when a client or an auditor asks why.
Estimatrix builds an analysis for every PWD Schedule of Rates item you add, and keeps the published rate untouched.
Where the quantities come from
The analysis reads the item's own specification and the headings it inherits: mix ratio (1:2:4, 1:1.5:3), concrete strength, sand fineness modulus, cement type, mortar ratio, plaster thickness and rebar grade. It then applies standard norms. For concrete, for example, the dry volume of materials is 1.54 × the wet volume, split by the mix ratio; see concrete material quantities.
Inside one schedule rate (made-up figures)
Tk 9,800
Worked out from norms and PWD basic rates.
Which rates are used
- PWD basic rates of the same edition, for all four zones. The line follows your project zone.
- Today's market prices from the Estimatrix market hub, shown in a second column.
- Wastage per material class (rebar, cement, sand, aggregate, bricks), set in Tools → Taxes & margins.
The balancing line
The published SoR rate is the official rate. Components worked out from norms rarely add up to exactly that figure, so Estimatrix adds a balancing line that makes the PWD-basis total equal the published rate.
To illustrate with made-up figures: if the materials, labour and equipment of an item add up to Tk 9,800 and the schedule publishes Tk 10,150, the balancing line is Tk 350. The BOQ keeps the official Tk 10,150, while the materials still flow into the material requisition and the market comparison.
Reading an analysis
Read it from the top, the way it will be questioned:
- Are the material quantities right for the mix and thickness in the description?
- Is the zone the zone of the site?
- Which line is largest? That is the price to confirm first.
- How far is the market column from the PWD column?
The worked articles on RCC concrete, brickwork and plaster show the arithmetic behind three common items.
Items without a standard breakdown
Ready-mix concrete, formwork systems, electro-mechanical items and lifts carry one composite line, which you can replace with your own breakdown.
Custom items
A custom item starts with its own rate-analysis template, and the analysed rate becomes the BOQ rate. Save it with the ★ button to your library: the item, its analysis and its measurement rows travel together to future projects.
Overtime and special labour
Use + Overtime on a day-rated labour line to price overtime hours at the day rate ÷ 8 × a factor of 1.0 to 1.1.
Market check
Turn on PWD vs Market to see, item by item, where the market rate is above the PWD rate: the overrun a contractor must absorb or negotiate. When market prices change, Estimatrix offers to update the analyses and shows the effect on the budget first.
Specialised items
Retrofitting items such as jacketing, micro-concrete, epoxy injection, chemical anchors and CFRP show a badge offering a technical consultation from Prime Base Engineering, because those works depend on calibrated equipment and experienced crews as much as on the rate.
From direct cost to a complete rate
The lines of an analysis add up to the direct cost: materials, labour and equipment. A complete rate has two more layers on top.
- Overhead and profit, as a percentage of the direct cost.
- VAT, as a percentage of the direct cost plus overhead and profit.
A new project in Estimatrix starts with profit 10%, overhead 3.5% and VAT 10% as the mark-ups built into the schedule rates. Set them to the values of the schedule edition you work with, under Tools → Taxes & margins.
With the starting values, a direct cost of Tk 1,000 becomes:
- 1,000 × 1.135 = Tk 1,135 with overhead and profit
- 1,135 × 1.10 = Tk 1,248.50 with VAT
So a complete rate is about a quarter above its direct cost. When a contractor says his cost is Tk 1,000 and the schedule says Tk 1,250, the two may be describing the same item.
Wastage, line by line
Each material line carries a wastage percentage, and the amount of the line is quantity × (1 + wastage) × rate. A new project starts with these allowances:
| Material | Starting allowance |
|---|---|
| Reinforcement | 2.5% |
| Cement | 1.5% |
| Sand | 2.5% |
| Stone or brick chips | 2.5% |
| Bricks | 3% |
Take one cubic metre of 1:2:4 concrete at the example prices of the concrete rate analysis.
| Material | Net | With wastage | Example rate | Amount (Tk) |
|---|---|---|---|---|
| Cement | 6.3 bags | 6.39 bags | 520 | 3,323 |
| Sand | 15.5 cft | 15.89 cft | 55 | 874 |
| Stone chips | 31 cft | 31.78 cft | 200 | 6,356 |
| Materials | 10,553 |
Without wastage the materials came to Tk 10,329. The allowances add about Tk 224, a little over 2%. They are small on one cubic metre and large on a whole building, so set them from what your own sites lose.
The factors behind the quantities
The quantities of cement, sand and chips depend on four numbers, kept under Tools → Dry-to-wet factors.
| Factor | Starting value | Range you can set |
|---|---|---|
| Dry volume of concrete | 1.54 | 1.40 to 1.60 |
| Dry volume of mortar | 1.33 | 1.20 to 1.40 |
| Volume of one bag of cement | 1.25 cft | 1.20 to 1.30 cft |
| Weight of one bag | 50 kg | 40 to 50 kg |
Change one and the generated analyses of the project are worked out again. Change them only when your specification or your department uses another figure, and note the reason on the cover of the estimate.
Keeping analyses complete
- Tools → Generate missing analyses builds an analysis for every item that does not have one yet.
- Tools → Market price check shows where the stored market prices have moved since the analyses were priced.
- Tools → SoR edition / re-price moves the whole BOQ to another edition of the schedule, with a restore point saved first.
Questions people ask
My components do not add up to the published rate. Is something wrong? No. Norms give the materials and labour of a typical job, and the schedule was fixed by the department. The balancing line holds the difference, so the bill keeps the official rate.
Can I change a quantity inside a generated analysis? Yes. The lines can be edited. On a schedule item the published rate still stands, and the market column shows what your change means in today's prices.
Which rate goes into the BOQ for a custom item? The analysed rate: the direct cost with the mark-ups above.
Does the analysis include carrying materials to an upper floor? Only if the item's description says so. Read the description before you add a lifting line of your own.
Mistakes we see often
- Changing a material price and expecting the official rate to move. On an SoR item the published rate stays; the market column shows the difference.
- Adding overhead and profit to a rate that already includes them.
- Comparing a rate from one edition of the schedule with basic rates from another.
- Leaving a composite line in place for an item that makes up a large share of the bill.
#rate analysis#pwd sor#market prices
Related articles

How to create a BOQ online with Estimatrix, step by step
From a blank project to a priced, tender-ready bill of quantities on the PWD Schedule of Rates: what to prepare, set-up, items, measurement, rates and export.
30 Oct 2026 · 7 min readRead

Measurement sheets: Enter-key entry, formulas, deductions and extra columns
Fast keyboard take-off in Estimatrix: Enter-key navigation, formulas inside cells, columns that follow the unit, deductions, multiplier columns and a worked example.
29 Oct 2026 · 7 min readRead

Rebar take-off in Estimatrix: bar sizes, unit weights and lapping allowance
Reinforcement items open in their own take-off: bars × diameter × length gives kilograms, with the unit weight shown, a lapping and wastage percentage and a summary by diameter.
28 Oct 2026 · 6 min readRead