Engineering articlesStructural retrofitting in Bangladesh: assessment, column jacketing and what it costs

How strengthening work is measured and priced in Bangladesh: column and beam jackets, footings and slab panels, BOQ quantities for one jacketed column, and 2026 costs.

By , Founder & CEOPublished 16 October 2026Updated 24 November 20265 min read

Structural retrofitting in Bangladesh: assessment, column jacketing and what it costs
Picture: generated with AI and edited by Estimatrix.

Thousands of factory buildings in Bangladesh have been assessed and strengthened since the garment-sector safety programmes began. Retrofitting is now ordinary civil engineering work, and it is priced differently from new work: member by member, not per square foot.

Assessment comes first

Nothing is priced until a Detailed Engineering Assessment (DEA) has found out what was actually built and the structural engineer has designed the strengthening from it. What a DEA involves is explained by Prime Base Engineering in what is a DEA, and what it costs in DEA cost in Bangladesh. For the estimator, the DEA's result is the starting point: a strengthening drawing, member by member.

Strengthening, priced by the member

Column, per m

Tk 42,000

Four sides, per metre of height.

The common methods

RC jacketing, steel jacketing and carbon-fibre (CFRP) wrapping strengthen single members; epoxy injection seals cracks; new shear walls, bracing or footings strengthen the building as a whole. The engineer chooses among them, and Prime Base Engineering's comparison of CFRP, RC and steel jacketing sets out which suits what. An estimate prices what the design shows, so the rest of this page is about measuring and pricing the work.

Measuring it in a BOQ

Item Unit Measured as
Surface preparation sqm column perimeter × height
Bonding agent sqm the same area as surface preparation
Chemical anchor dowels nos from the design
Jacket reinforcement kg bar take-off
Micro-concrete cum (jacketed section − existing section) × height
Formwork sqm jacket perimeter × height
Curing sqm jacket surface

What it costs in 2026

These are the rates behind the Estimatrix budget calculator. They are complete rates, with rod and cement, set from billed work on private industrial and government jobs in 2025 and 2026.

Work Most likely cost
RC jacket to a column, four sides Tk 42,000 per metre of height
RC jacket to a beam, three sides Tk 38,000 per metre of span
Strengthening a footing against punching shear, with its short column Tk 2,20,000 per footing
Breaking and recasting or strengthening a slab panel Tk 1,100 per sft of panel

Steel jacketing costs about 15% more than RC jacketing, and CFRP wrapping about 45% more. All figures exclude VAT, AIT and design fees.

A worked example: jacketing 24 ground-floor columns 4.6 m high costs about 24 × 4.6 × 42,000 = Tk 46 lakh.

In Estimatrix

Link the bonding agent and curing measurements to the surface preparation, so the areas always match, and use the rebar take-off for the cages. The PWD Retrofitting Schedule of Rates covers many of these items, and Estimatrix has templates for column jacketing, epoxy anchors and dowels. For a first figure for your own building, use the budget calculator.

A worked budget for a ground floor

Ground-floor columns are the usual weak point. Take the 24 columns of the example above, 4.6 m high, and add the strengthening of their footings.

  • Column jackets = 24 × 4.6 × 42,000 = Tk 46.4 lakh
  • Footings = 24 × 2,20,000 = Tk 52.8 lakh
  • Together = about Tk 99 lakh

If beams and a slab panel are in the design too:

  • Beam jackets, 20 beams of 7 m = 20 × 7 × 38,000 = Tk 53.2 lakh
  • One slab panel of 2,000 sft = 2,000 × 1,100 = Tk 22 lakh

The same column jackets by another method: steel jacketing at about 15% more is 46.4 × 1.15 = Tk 53.3 lakh, and CFRP wrapping at about 45% more is 46.4 × 1.45 = Tk 67.2 lakh. The method is chosen by the design, not by the price.

All figures exclude VAT, AIT and design fees, and they are a first budget. A firm price comes from the measured BOQ of the approved design.

BOQ quantities for one jacketed column

A column of 400 × 400 mm, 3.0 m clear height, jacketed on four sides. The jacket thickness comes from the design; 100 mm is used here only to show the arithmetic.

Item Working Quantity
Surface preparation 4 × 0.4 × 3.0 4.8 sqm
Bonding agent same area 4.8 sqm
Micro-concrete (0.6 × 0.6 − 0.4 × 0.4) × 3.0 0.60 cum
Formwork 4 × 0.6 × 3.0 7.2 sqm
Curing jacket surface, 4 × 0.6 × 3.0 7.2 sqm

Dowels are counted from the drawing and the jacket bars are taken off bar by bar. For 24 such columns the micro-concrete is 24 × 0.60 = 14.4 cum and the formwork 172.8 sqm.

Notice that the formwork and the curing follow the new, larger section, while the surface preparation and the bonding agent follow the old one.

Questions people ask

Why is retrofitting not priced per square foot? Because two buildings of the same area can need very different work. The cost follows the members that are strengthened.

Why do the formwork and the bonding agent have different areas? The bonding agent goes on the old surface, so it follows the existing section. The formwork and the curing hold the new jacket, so they follow the larger section. On the 400 mm column above that is 4.8 sqm against 7.2 sqm.

What should be recorded on site? Photographs of each prepared surface, the anchor test results, the batch numbers of the materials, the cube or cylinder results and the curing dates. These records are what an auditor asks for.

Getting help

Retrofitting needs calibrated equipment, specialised chemicals and experienced crews. Prime Base Engineering carries out assessment, design checking and turnkey strengthening; ask for a consultation.

#retrofitting#jacketing#dea#strengthening

Related articles